Beware the Lowest Price
Awarding contracts to the lowest bidder is optimistic at best, dangerous at worst. So why do we keep doing it?
There are many reasons. To pick just one: we believe it works in "real" engineering - making bridges, roads and buildings.
But it doesn't. Although it is widely used in engineering; it's not widely successful!
The Truth about Engineering
The latest issue of e.nz, published by New Zealand's Institute of Professional Engineers, reports that "the indiscriminate urge for lowest price" leads to "late and unsatisfactory completion, disputes and litigation". (Almost sounds like software!)
The New Zealand Construction Industry Council says that "the lowest-bid approach is compromising design quality and integrity, health and safety, training, the environment... [Furthermore,] the lowest bid approach encourages unsustainable markets" [1].
Discussing solutions to these problems, e.nz explains that: "A substantial culture change is involved in progressing towards best practice in procurement. All stakeholders must accept that they have a duty to collaborate towards a common objective: the full satisfaction of the project's objectives, in exchange for fair rewards for all who contributed." [2]
Why is the Lowest Price Dangerous?
The lowest price is dangerous because you don't know why it's low. In the software industry, a company may offer a low quote for any of the following reasons:
1. They have misunderstood the difficulty of the task [3].
2. They understand the task; the estimate is low simply because software estimation is inherently difficult.
3. They understand the task, and are deliberately bidding low because they're eager (or desperate) for your business.
4. They understand the task, and have outstanding skills and technology which will allow them to complete it quickly.
Only the last reason is a good one. The others, to greater or lesser degrees, may all threaten your project. Yet in terms of price, they look the same.
So How Do You Tell the Difference?
You have to base your decision on assessments of the supplier's capability: the quality of their staff, the quality of their technology, and their track record.
Price tells you nothing about capability. A low price may signal superior capability (reason 4), inferior capability (reason 1), desperation (reason 3), or nothing (reason 2).
A Better "Real" Engineering Practice to Emulate
If we want to emulate "real" engineering, we would be better to take our lead from the US federal government. (I never thought I'd say that :-) Since 1972, price-based selection for engineering services has been prohibited for federal government agencies, with selection being based on supplier quality instead [4]. The approach has proved highly successful and has been widely emulated by state governments.
I believe the US approach reflects an understanding of the risks noted above - that price tells you nothing about capability.
The US approach may also reflect an awareness of just how embarrassing price-based selection would be after a major engineering disaster. Imagine a TV interview shortly after the collapse of a bridge:
Reporter: So how did you award the contract?
Official: We… errrr...chose the cheapest.
Indeed.
Why don't we ask the same question after a software project collapses?
References
For another perspective, see this Canadian document: http://www.peo.on.ca/publications/DIMENSIONS/marapr2001/ma01price_consult.pdf Like New Zealand, Canada has experienced a "leaky building" scandal in which price-based procurement was a contributing factor.
More on the Brooks Act(s):
If you're interested in the fact that the (engineering) Brooks Act covers design, but not (as far as I know) construction, read these articles by Jack Reeves: http://www.developerdotstar.com/mag/articles/reeves_design_main.html See this page on my site too.